Saturday 8 March 2008

More March Photos





March Progress - much progress




The foundations were poured, walls built and steels erected whilst we were away skiing! In only a couple of days they had most of the timber in place for the roof. The glass is on order and is a 4 week lead, which means the job is on hold until it arrives. The majority of the flat roof can be laid next week.

Tuesday 5 February 2008

February Progress - Polish Builders & Foundations



We have a new set of builders. So far so good. They quickly demolished the old utility room and dug the foundations in only a day.